Project included: The demolition of existing and installation of a new clarifier. Modifications to the scum channel at the bottom of the clarifier tank to eliminate 270 degrees of the channel to provide additional support for the clarifier center column. Sandblasting and painting of existing weirs, scum baffles, and scum baffle supports. Installation of a new clarifier control panel and all electrical wiring. Also included were startup and training.
Owner | City of La Junta |
---|---|
Engineer | Farnsworth Group |
Value | $175,000.00 |
Contract Duration | 180 Days |