Project included: New piping, valves, electrical, and instrumentation work to revitalize the blowdown piping system.
| Owner | Parker Water and Sanitation District |
|---|---|
| Engineer | Dewberry |
| Value | $150,000.00 |
| Contract Duration | 54 Days |
Project included: New piping, valves, electrical, and instrumentation work to revitalize the blowdown piping system.
| Owner | Parker Water and Sanitation District |
|---|---|
| Engineer | Dewberry |
| Value | $150,000.00 |
| Contract Duration | 54 Days |